Payment period and accrual of late payment interest in public contracts: latest controversial Supreme Court ruling
Supreme Court Judgment no. 5938/2024, which confirms its doctrine on the payment period and the accrual of late payment interest in public contracts, is examined. This doctrine, which establishes a general 60-day period, raises doubts as to its compatibility with Directive 2011/7/EU and with the CJEU’s case law.